Mid and West Wales Fire and Rescue Authority

Fire Authority crest

MEETING OF THE RESOURCES COMMITTEE

Monday, 26 July 2004

FIRE SERVICE HEADQUARTERS,
LIME GROVE AVENUE, CARMARTHEN

Attendance

Chairman: T E Evans
Vice Chairman: J J J Davies
Members:

Cllrs: J S Allen-Mirehouse,Mrs T Devichand, Mrs J Dudley,C Morgan, D Price, D C Prothero,G Seabourne, D G Sullivan, T Theophilus, J D A Thompson

In Attendance: Cllr B J Hall
Apologies: Cllr Mrs P Spender
 

Contents

2. TO APPOINT A VICE CHAIR FOR THE MUNICIPAL YEAR 2004/2005


1. DECLARATION BY MEMBERS OF ANY PERSONAL INTEREST

None were declared

2. TO CONFIRM AS A TRUE RECORD THE MINUTES OF THE MEETING HELD ON 26TH APRIL 2004

The minutes of the meeting held on 26th April 2004 were received and confirmed as a true record

3. TO RECEIVE THE TREASURER’S BUDGET MONITORING REPORT FOR THE FINANCIAL YEAR 2004/05

Revenue Monitoring Report for the period 1st April to 30th June 2004

The Treasurer reported that the detailed budget had now been completed with the allocation of the £300k IRMP savings within the Employees budget of which £200k was from full-time vacant posts and £100k from reduced retained activity. The total expenditure to date included actual expenditure recorded on the financial ledger and known commitments to 30th June. An underspend for the period of £427k was noted, with the forecast expenditure for the year remaining within the budget overall. Expenditure had been delayed on Central Training (within the Employees budget), Leasing and Pensions, but these would even out as the year progressed.

The profiled budget to June for uniformed pay had been based on current pay but the estimated commitments to the year end had allowed for payment of the full Stage 2 and Stage 3 pay increases within the year.

The Treasurer reported that within the Employees budget to 30th June there had been a net overspend on uniformed pay of £18k, which when extrapolated gave a forecast overspend of £85k for the whole year, attributable to retained pay costs. This had indicated that it was likely that the IRMP savings would not be fully realised in the year with the underlying causes being the high retained costs, in spite of the AFA call reduction strategies, which would be subject to clarification from activity data.

Capital Monitoring Report for the Period 1st April to 30th June 2004

The expenditure to date on Capital Projects was reported against the Approved Capital Programme and the 3-year Approved Capital Programme was noted for information.

RESOLUTION

It was RESOLVED that

The Treasurer’s Budget Monitoring Report and the Capital Monitoring report for the period 1st April to 30th June 2004 be received and approved.

4. TO RECEIVE THE TREASURER’S REPORT ON THE ACCOUNTS FOR THE FINANCIAL YEAR ENDED 31ST MARCH 2004

Revenue out turn for the period 1st April 2003 to 31st March 2004

The Treasurer reminded Members that the expected out turn for 2003/04 had been reported to the Resources Committee on 26th April 2004 and that the 2003/04 Statement of Accounts, which was now nearing completion, indicated that the final figures would show no significant changes. It was noted that the Revenue expenditure for the year ended 31st March 2004 was £36.160m.

Capital out turn report for the period 1st April 2003 to 31st March 2004

It was noted that the total capital expenditure was £1.197m, which was financed mainly by loan, using Basic Credit Approval of £0.904m. The Dyfed-Powys Police contribution to the joint project at Crymych amounted to £0.082m for 2003/04. Government grants totalling £0.110m had been received to fund New Dimension building projects and the new telephone system and in addition, direct revenue financing of £0.101m had been used to finance vehicles and equipment.

Members were informed that the Statement of Accounts, subject to audit, would be presented for approval by Members at the September meeting of the Fire Authority. The deadline for approval of the Statement of Accounts remained at 30th September for the 2003/04 Accounts.

RESOLUTION

It was RESOLVED that

The Capital and Revenue out turns for the period 1st April 2003 to 31st March 2004 be received and approved.

5. TO CONSIDER THE REPORT ON THE HEADQUARTERS ACCOMMODATION PROJECT

The Chief Fire Officer provided Members with an update on the progress of the new Headquarters Accommodation Project at Lime Grove Avenue, from which it was noted that the planning and design processes was ongoing, and that a formal planning submission had been made to the local authority, the result of which was awaited. Detailed drawings were currently being drawn up to support the building regulations application, and once planning approval had been granted, it was proposed that a formal tendering exercise would be undertaken in the late summer or early autumn.

Committee were reminded that this project had been included within the approved Capital Programme for the current and 2005/06 financial year, with funding allocations made in the amounts of £750K and £1.342 million respectively. Meeting the current project timetable, and thereby the expenditure profile, would require a start to be made on the site by no later than November 2004. This was an ambitious timetable, and whilst it remained achievable, it would require all current components of the final design, planning, building control and tendering procedures to be completed by no later than the end of October.

In the event that this timetable was subject to slippage during any of the current preparatory stages, it would be necessary to re-schedule the expenditure profile for the project. If this proved to be the case, arrangements would be made to bring forward capital projects currently scheduled for the next financial year, in order to optimise the use of available capital resources in the current year, and then to reallocate funds released from next year towards the Headquarters project.

Committee were aware that it was extremely difficult to judge whether the project timetable would be realisable as much depended upon progress in gaining planning and building control approval, processes which would need to be complete in order to inform the production of tender specification documents. In the event that slippage occurred, Members endorsed in principle the re-phasing of the approved capital programme in order to ensure that available capital allocations would be fully utilised. Should this become necessary, further detailed reports would be presented to Committee on the affected schemes. In the meantime it was agreed that officers would undertake the necessary preparatory works to ensure that should re-phasing be necessary, substitute projects were at the appropriate stage of readiness in order to take up any available capital resources in the current financial year.

RESOLUTION

It was RESOLVED that

the updated report be received and that the principle of re-phasing the projects within the current and next year’s capital programme be endorsed, subject to detailed reports being submitted to Committee at the appropriate stages.

© Mid and West Wales Fire and Rescue Service  •  Disclaimer  •  Privacy Policy  •  Linking Policy Add To Favourites